Permits & Approvals
How we handle zoning, permits, conservation authority approvals and inspections.
See the service →
Planning Signs Off Before Building Will Look
A new house in Orillia goes past two City desks before it is issued, and an inspector at fifteen stages after. The schedule lives in that sequence.
Orillia building permits for a new house are not one application. They are two, to two different parts of the City, followed by up to fifteen inspections that each have to be booked two business days ahead. Most of the waiting on an Orillia build is not the City reading drawings; it is one step not being ready when the next one is due.
We are A&R Design Build. We have handled planning applications, permits and inspections as part of our builds across Central Ontario since 1973, and Orillia is part of the region we serve from our base in Innisfil. Here is the City of Orillia process in the order it actually runs, from the documents the City itself publishes.
The City of Orillia’s own lists, side by side.
New construction, additions and major renovations. Structural changes, including adding or removing walls. Garages, decks and sheds larger than 15 m² (162 sq ft). Plumbing and HVAC work. Installing or changing a septic system. Demolition.
Garages, ADUs and bunkiesPainting, flooring and non-structural repairs. Fences, except pool enclosures. Windows or doors replaced with the same size. Cabinets installed without changes to plumbing.
Ask us if you are unsureThe City’s guide for a new dwelling, BD.F.413, opens with an instruction that shapes the whole timeline: a Zoning Certificate is required before you apply for a residential building permit. The certificate is a Planning document, applied for through the City’s public portal or by email to the planning office, and it is checked against the zoning before anyone in Building opens the drawings.
What the Zoning Certificate needs is short: the application form and a site plan showing the proposed building, any existing buildings, the setbacks to every property line, and the existing driveway, parking and landscaped areas, plus detailed elevations. Short does not mean quick to prepare. The site plan has to be right, because the setbacks on it are the ones the house will be built to.
Then the building permit. For a detached, semi-detached or townhouse dwelling, the City’s guide asks for:
The guide adds one line for low-lying land: properties in the City’s Flood Hazard Overlay Zone must incorporate flood-proofing in line with the Ontario Building Code, under the City’s Building in Flood Plains policy. If your Orillia lot is near the water, ask about the overlay before the drawings are started, not after.
The permit is not issued until the money side is settled, and for a new house the permit fee is the small part. BD.F.413 lists the typical charges together: building permit fees, City development charges, education development charges for the Simcoe County District School Board and the Simcoe Muskoka Catholic District School Board, and a lot grading deposit of $2,000.
The City’s development charge pamphlet says its charge is payable on the date the building permit is issued; from July 1, 2026 it is $31,771.58 for a single detached dwelling. The lot grading deposit breaks down as a $350 review fee that stays with the City and $1,650 that comes back once the grading is certified. Fees can be paid by cash, cheque, debit or credit card, with credit cards accepted online only and a 2.4% convenience fee on top.
Once it is issued, the permit is worked off on site. The City of Orillia lists fifteen inspection stages and requires that each one is booked before construction moves to the next phase.
The booking rule is the part that sets the pace. Every inspection needs at least 48 hours’ notice, and the count starts on the following business day, not counting weekends, holidays or office closures. A request made on a Friday afternoon is a request for Wednesday. The City asks for the permit number, the address, the type of inspection, a date and time preference, and the builder’s or superintendent’s contact details.
Miss the mark and it costs. When work is incomplete or needs corrections, the City charges a re-inspection fee with a minimum of $171.78. Across fifteen stages, a builder who books inspections for work that is not ready can add both money and days to an Orillia build.
The last two stages matter most to the owner. The City says plainly that no occupancy is permitted until an Occupancy Permit is issued. Plan the move, the mortgage draw and the sale of your current house around that inspection, not around the day the painters leave.
Planning and permit approvals are step five of our twelve-step process. On an Orillia house, it runs like this.
We check that the lot is inside the City of Orillia, what the zoning allows, and whether the Flood Hazard Overlay Zone touches it, before the design is fixed.
We prepare the site plan and elevations and apply to Planning, so the setbacks are approved before the permit drawings are finished.
Drawings, the stamped grading plan, the energy summary and the engineered layouts go to Building together, with your authorization for us to apply.
Inspections are booked to the construction schedule as each stage is ready, through to the occupancy permit and the final walk-through with you.
Laura McAdam leads design, planning applications and municipal approvals for our clients, turning ideas into buildable plans. Darcy McMahon coordinates construction from framing to completion, including the schedules the inspections have to fit into. Rene Ouellet Jr. oversees site preparation, excavation and foundations, which is where the first three Orillia inspections happen.
If you would rather run the Orillia building permits yourself, the City is helpful and its guides are clear; call 705-329-7258 or write to the building office. If you would rather hand the whole sequence to the people building the house, that is part of what we do. A&R Design Build Inc. is HCRA-licensed (licence #B46716) and has been a Tarion Registered Builder since 1983.
Yes, for residential work. The City’s new-dwelling guide says a Zoning Certificate is required before you apply for a residential building permit. It is applied for through the Planning side of the City, with a site plan and detailed elevations.
Through the City’s e-Permit portal or with the inspections staff, at least 48 hours in advance, counted from the next business day. Have the permit number, the address, the type of inspection, your preferred date and time, and the builder’s contact details ready.
The City charges a re-inspection fee, with a minimum of $171.78, when work is incomplete or corrections are needed.
Garages, decks and sheds larger than 15 square metres (162 square feet) need one. Fences generally do not, except pool enclosures. Painting, flooring, non-structural repairs and same-size window or door replacements are also exempt.
Not before the City issues an occupancy permit. The City is clear that no occupancy is permitted until it does. Occupancy is the 14th of the 15 inspection stages, with the final inspection after it.
For a new dwelling the City lists building permit fees, City development charges, education development charges for both school boards, and a $2,000 lot grading deposit, of which $1,650 is refunded after the grading is certified. The development charge is payable when the permit is issued.
How we handle zoning, permits, conservation authority approvals and inspections.
See the service →What happens, and in what order, on a custom build.
Read the post →Tell us about the lot and the house. We will reply within two business days and tell you honestly what the City will need.